Vibration Causes Nerve Damage (Britain)

A Nottinghamshire aerospace engineering company has been ordered to pay more than £190,000 in fines and costs for failing to protect its employees from the effects of vibration, after 24 workers were diagnosed with debilitating nerve conditions.

Nottingham Crown Court heard that although HSE was notified of an employee being diagnosed with HAVS in 2010, the issue dated back to 2005 when the company’s health and safety committee asked it to carry out a suitable risk assessment for exposure to vibration, and act on the result. An assessment of the company’s tools took place in 2006 which identified some, including drills, grinders and hammers, posed a high risk from exposure to vibration. However, they were not taken out of service and no controls were put on their use until 2010. In addition, some employees used their own tools, which were also not assessed and therefore no controls put in place. HSE found that although the company provided some health surveillance for employees, it was not sufficient to identify symptoms early and refer individuals to occupational health specialists for timely diagnosis and management.

The symptoms of HAVS syndrome include blanching and numbness in the fingers, especially in the cold, as well as pins and needles, which can be extremely painful. This is due to damage to the small blood vessels and nerves supplying the hands. Sufferers can have difficulty picking up small objects and performing tasks such as doing up buttons. As sufferers cannot be exposed to cold without pain it can restrict some work and hobbies such as fishing, cycling or gardening.

Sufferers of carpal tunnel syndrome also experience pain and pins and needles, especially at night, and a reduction in grip. An operation is normally needed to release the nerve, although this is less successful if they have been exposed to vibration.

Speaking after the hearing, HSE Inspector Dawn Smith said:

“SPS Aerostructures Ltd was, from 2005, regularly being made aware that employees were suffering from vibration-related symptoms. They were being supplied with this information directly from staff and from their Occupational Health Nurse. However, they chose to ignore this information and allowed employees to work unrestricted with high risk tools, or their own tools.”

“The company was slow to implement improvements even after HSE’s involvement and had to be issued with an Improvement Notice in 2011 to ensure compliance.”

“Adequate assessment of the risk from vibration, provision of tools with lower vibration levels, and a good system of work would have ensured workers were not over-exposed to vibration. A better health surveillance system would also have identified problems earlier, and symptoms could have been managed to prevent them getting worse.”

Prosecution was for breach of Section 2(1) of the Health and Safety at Work etc Act 1974, which states: “It shall be the duty of every employer to ensure, so far as is reasonably practicable, the health, safety and welfare at work of all his employees.”

The HSE press release is here.

Petrol Leak Enforcement (Britain)

A company which distributes fuel across a national network of pipelines has been fined after 35,000 litres of unleaded petrol erupted from pipework due to a joint failure.

Britain’s Health and Safety Executive determined the fuel, which escaped under high pressure and rained down on the site, could have resulted in a major fire and possible explosion. The leak also led to a significant clean-up operation, including the specialist decontamination of land.

HSE found that the pipework involved had been reconfigured and replaced as part of a major engineering project finished a week before. However, before being put to use the joints and fittings were not properly commissioned and tested.

British Pipeline Agency Ltd, of Alexandra Road, Hemel Hempstead, Hertfordshire, was fined £30,000 with costs of £58,606 after pleading guilty to breaching Section 2(1) of the Health and Safety at Work etc Act 1974.

After the hearing HSE inspector Alex Nayar said:

“This was a very serious incident with the potential to be extremely dangerous. It was also one that could have been avoided very simply.

“When plant is changed or modified it has to be tested and commissioned before being put into operation. That did not happen. If done properly it could have identified the fault.

“The leak posed two major hazards, a fire or a vapour cloud explosion. It is extremely fortunate that neither happened in this case as the outcome could have been much worse.”

The HSE press release is here.

Asbestos Enforcement (Britain)

Britain’s Health and Safety Executive found recommendations made in an asbestos removal plan were ignored by the contractor engaged to manage asbestos during demolition works. The asbestos spray coating on the main hall walls was chiseled off using power tools without any screens, enclosures or air extraction systems in place. Asbestos-containing material was bagged and carried to a skip outside. The contractor then notified the main contractors that the asbestos removal work on the main hall was finished, but when the project agents and main contractors visited the next day, they found the hall covered in dust and patches of asbestos material still on the wall.

The court heard that HSE found a catalogue of failings in the way the work had been planned and carried out. The exact location of asbestos material wasn’t identified and the work only took one day to complete rather than the planned seven. Risk assessments were too generic; enclosures, segregation and containment measures were inadequate; plans lacked detail; access and transit routes through the buildings weren’t clear; employees lacked specific instruction, and there was no reference to the original asbestos survey in the plan.

HSE experts concluded the company’s safeguards to control the asbestos risks were seriously inadequate leading to an unnecessary release and spread of dangerous asbestos fibres and dust.

The plan and risk assessment for the asbestos removal work in the building’s boiler room were also found to be confused and a decontamination unit was not powered. HSE served a prohibition notice to halt the work on the boiler room until the unit was properly powered and working.

Angus Group Ltd of Neilson Road, Paisley, Scotland, was found guilty of eight breaches of the Control of Asbestos Regulations 2006, and was fined a total of £109,000 and ordered to pay a further £42,100 in costs.

The HSE press release detailing the specific offences is here.

Decommissioning Project Fatality (Britain)

Joint investigation by Britain’s Health and Safety Executive (HSE) and the South Wales Police identifies fatal head injuries had occurred because a company had failed to adequately plan and resource decommissioning work. During dismantling of a section of industrial pipework at factory premises in Llantrisant in June 2010, a structure, weighing around 300kg, had collapsed and struck an employee (an engineer) who was assisting the specialist contractors.

During the decommissioning, the factory had become a construction site with the company electing to plan, manage and monitor the project themselves instead of appointing a competent Principal Contractor. As a consequence, it had overlooked various hazardous tasks such as the removal of overhead industrial pipes and their supporting structures. This work consequently fell to the in-house engineers because they had not contracted the specialists to do it.

The court was told that the employee’s work had not been adequately planned, risk assessed, communicated or monitored by management, and that the various safety systems the company used to manage its specialist contractors had not been used to manage its own engineering staff on the same site.

The police and HSE investigation established that because no written plan was provided to the company team explaining how the structure was to be taken apart, various bolts and structural elements were removed in an unsafe sequence. This is what led to the eventual collapse.

The Court also heard that a production manager for the factory was in charge of the hazardous decommissioning project, despite never having done this work before or having received any formal training. Furthermore, a safety officer only visited once or twice a fortnight and was based in Somerset.

Speaking after sentencing, HSE inspector Liam Osborne, said:

“Gavin Bedford, a young hard-working and highly-regarded engineer, was killed because of Gerber’s basic corporate failure to plan, manage and monitor a construction project. “Any demolition or dismantling work must be set down in writing and strictly monitored – as the law requires. It is also basic common sense.”

“If Gerber had given enough time at the beginning to think through what needed to be done, and how it should be done, then Gavin would still be here today.”

Prosecution was carried out under Section 2 (1) of the Health and Safety at Work etc. Act 1974, which states: “It shall be the duty of every employer to ensure, so far as is reasonably practicable, the health, safety and welfare at work of all his employees.”

The fine was £80,000, with an order to pay costs of £75,000.

The HSE press release is here.

Land Reform (Scotland)

Published May 2014 – Land Reform Review Group Final Report – The Land of Scotland and the Common Good

This is the final report of the independent Land Reform Review Group set up by the Scottish Government in 2012.

The Review Group’s remit is to examine the role of Scotland’s system of land ownership in the relationship between the people and land of Scotland, and make proposals for land reform measures that would:-

“* Enable more people in rural and urban Scotland to have a stake in the ownership, governance, management and use of land, which will lead to a greater diversity of land ownership, and ownership types, in Scotland

* Assist with the acquisition and management of land (and also land assets) by communities, to make stronger, more resilient, and independent communities which have an even greater stake in their development

* Generate, support, promote, and deliver new relationships between land, people, economy and environment in Scotland”

The Report has nine Parts. In the first, the Group sets the context for the rest of the Report by clarifying the scope of the Group’s review and defining its use of terms including, for example, what is meant in the Report by ‘the public interest’. The Report then has seven main Parts, 2-8, dealing with the main land reform issues considered by the Group. In Part 9, the conclusions from those Parts are discussed in terms of the three broad objectives in the Group’s remit, and there is a summary list of the Group’s Conclusions and Recommendations from each Part of the Report.